Several Steps of Replacement and Maintenance of Slewing Bearing
Release time:
2022-03-01
Source:
1. Welding bracket and other preparatory work
(1) Under the machine. Isolate the maintenance area a distance before operation. Splice the portal frame with 24# channel steel on the ground, and remove it from the welded middle beamslewing bearingThe lifting lugs used by the chain block. After welding on the machine, add channel steel and angle steel fixing brackets at the bottom and diagonally to ensure replacementslewing bearingRack level, to avoidslewing bearingTilt and cut the base, the angle is too large and difficult to get out of the groove.
(2) inMachineOn. The jacking support shall be cut into large lifting lugs, polished and smooth, and the lower part shall be supported by long ribs with the same thickness as the base. Welding3 integral lifting lugs, with removedslewing bearingThe shelf corresponds. The two lifting lugs are welded to the counterweight of the door tail, and the lifting lugs of the second rear support seat are used for support10t chain gourd.
(3) Inside the center slip ring. After cutting off the high-voltage power supply again, remove the middle slip ring and each control circuit, use thick waterproof glue to make good joints, and mark with marking paper. The middle slip ring is wrapped and fastened with asbestos cloth to prevent damage to the circuit by electric welding and gas cutting sparks. Front, rear, left and right four-point welding single ear for adjustment and installation of newslewing bearingThe radial position. Remove swivel anchor and seal with iron plate. Remove24 centralized lubricating oil pipes and fold them up. Check other positions of the center slip ring for complete removal or impactslewing bearingPull out and remove and fix it in time.
(4) Positioning. Hoist the crane to the anchor position that does not affect the loading and unloading position, connect the windproof cable with the anchor position, and drop the windproof iron wedge. Adjust the amplitudeLimitLarge location43m, the boom faces the shore (positioned during installation, and the wharf wind direction is parallel to the boom, so that the gantry crane does not bear the wind). Removalslewing bearingoil pan, clean the oil pan andslewing bearingGrease.
2. Lifting insurance and testing
(1) jack up the use of money safety bolt. Remove 80 sets of internal and external fixing bolts respectively. Due to excessive pre-tightening, the nut can be cut longitudinally with gas cutting and disassembled in 2 times. Remove the inner and outer 2/3 fixing bolts for the first time, and remove the remaining 1/3 bolts before the maintenance site is ready for windless jacking. At the same time, insert 1/3 of the safety bolt (M42680) into the external bolt hole and carry out the jacking test before jacking.
(2) As jacks play an important role in the jacking process, it is necessary to prepare 6 320t jacks, two of which are for standby. Place the bottom of the jack flat on the jacking point of the jacking support and align it with the jacking support above. After all fixing bolts and upper and lower connections are removed, perform pressure test with four jacks at the same time to ensure that each jack struggles and lifts at the same speed; otherwise, replace the spare jack.
3. Jacking process
Because the wind in the jacking process will cause a certain risk, so to ensure that the wind is small enough, can be in.MoreShort time to complete the jacking.
Jacking again via reverse gear282mm, then stop jacking up,ButThen measure the height of the four-point position and adjust the same. Clearance between crescent cushion block and jacking cushion block with anti-pressure relief fuseAfter 3mm, the jacking pressure is released at the same time, and the rigid support is used instead of the oil pressure as the rigid support of the gantry crane. Then measure the height of the upper and lower support seats with a tape measure, cut off 24# channel steel of the same length and weld it on the side of the jack to do longitudinal stretching insurance. The front of the door is supported by a 100 in both directions.*1008 angle steel is used as rigid anti-fretting fuse to prevent shearing force generated by door rotation; two 10t reverse chain bidirectional stay cables are used as flexible fuse to prevent rotation at the rear side of the door to absorb part of seismic force. There should be enough space on the rack to remove the largeslewing bearing.
Slewing bearing